The
Risk Maturity Model
In
2002, the UK MoD Defence Procurement Agency (DPA)
commissioned HVR to conduct a full programme of risk
management capability assessments for the Integrated
Project Teams (IPTs) responsible for its thirty major
military equipment acquisition projects. The total
acquisition value of these projects is approximately
£60 billion. The projects affect all three armed
services and include Eurofighter, Bowman, CVF and
the Astute class submarines.
The
DPA had identified a need to measure risk management
capability when it recognised that project approvals
had been achieved on a number of projects on which
risk had subsequently proved to be too high. As a
result, the proportion of projects exceeding their
envelope of cost and/or schedule estimates was higher
than forecast. The implications were that either risks
were not being adequately managed following project
approval or that the risk assessments provided at
project approval decisions were not realistic.
The
HVR Risk Maturity Model (RMM) was used to
assess the risk management capability of each major
IPT. Following each assessment the IPT received a
short report summarising the findings and identifying
key actions for improvement. A small proportion of
IPTs were found to already be at RMM Level 4. These
teams were used by the DPA as points of contact for
other teams to learn from.
 |
 |
As
the number of assessed IPTs grew, a number of insights
emerged that were important at a corporate level.
In particular, some process areas started to emerge
as being common points of weakness. An early example
of this was evidence of weaknesses in the models
used for quantitative analysis; weaknesses that
were particularly significant in the context of
the strategic approach to project approvals. Common
areas of weakness amongst IPTs were tackled with
corporate level corrective responses.
Early
assessments were also used to transfer audit skills
from HVR to the DPA’s own risk management
specialists. As a result, most MoD assessments are
now conducted by DPA internal staff. Risk Maturity
Assessments are also used to provide assurance as
to the integrity of risk data at key corporate
governance points. Since April 2004 it has
been the DPA’s policy that any Category A,
B or C project (£20 million +) must have a
risk maturity level 3 capability prior to seeking
“Main Gate” approval.