Project
schedule risk analysis is a common application
of the Monte Carlo simulation technique.
A network of activities, usually derived from the
project plan, is combined with risks, typically from
the project risk register, to form a risk model. The
Monte Carlo process then analyses the schedule,
by randomly simulating the effects that a mixture
of good and bad luck may have on the outcome of key
milestones and the project completion date. Iterations
in which there is a disproportionate amount of bad
luck result in a relatively late completion and, similarly
iterations in which there is a run of good luck result
in much earlier completion. The result is that the
simulation output should include all the possibilities
that are, realistically, possible. Typically, this
output is shown on an S-curve graph of the type shown
below.
 |
 |
Monte
Carlo schedule risk analysis is particularly
useful at strategic points during a project when managers
need a realistic understanding of the time at which
key milestones can be achieved. They can also be used
to distinguish between targets (by which an early
finish might be realistically incentivised) and expected
durations or commitments. A further advantage is that
statistics from the simulation can be used to identify
which activities and risks are the ones that have
the most influence over the project’s schedule
performance. This is an insight that is not available
from simpler approaches to risk analysis that do not
model risks quantitatively in the context of the overall
plan.
Monte
Carlo schedule risk analysis is therefore a powerful
approach to project schedule performance forecasting.
However, as with all modeling, it does have a potential
downside; if the data input is poor the output is
likely to be misleading. Preventing this problem requires
careful attention to the development of the model
and estimates. Usually, the key things to get right
are:
•
Structuring the activity network that forms the
basis of the risk model
• Making realistic estimates for activity
uncertainty
• Selecting and positioning risks
• Estimating risk probabilities and impacts
• Introducing appropriate correlation of risks
and activities
• Identifying and reporting major assumptions
Detailed
advice on each of these points can be obtained from
papers that can be downloaded from this site or from
the APM’s PRAM Guide. As an example, the paper
that can be downloaded below includes check lists
of questions that can used to verify whether or not
the modeling is of good quality.
Download
a paper – “Schedule
Risk Analysis: critical issues for planners and managers”
HVR
recommends Pertmaster as a schedule risk
analysis tool. Details on Pertmaster and
other products can also be found on the Risktools.com
website.
Contact:
martin.hopkinson@hvr-csl.co.uk