 |
 |
Cost
risk analysis is, perhaps, the most common application
of the Monte Carlo simulation technique in
project management. Usually, a cost risk model
is built using lines items of cost defined at a relatively
high level of the cost breakdown structure. The planned
values for these lines of cost are then substituted
with uncertainty estimates (typically defined by probability
distribution functions like those illustrated below).
The model is then augmented with risks from the project
risk register which are additional potential sources
of cost. The structure created is likely to be similar
to that illustrated in the figure below-right, taken
from the APM’s PRAM Guide. Some projects may
make the simplifying assumption that uncertainties
in the planned lines of cost are negligible in comparison
to the potential impact of risks. In this case, the
first section of the model would be removed and the
purpose of the analysis of risks only would be to
estimate the financial reserves required over and
above the planned costs.
The
Monte Carlo process analyses the cost
risk model by randomly simulating the effects
that a mixture of good and bad luck may have on the
overall cost. Iterations in which there is a disproportionate
amount of bad luck result in relatively high costs
and, similarly iterations in which there is a run
of good luck result in much lower costs. The result
is that the simulation output should include all the
possibilities that are, realistically, possible. The
output is usually displayed as an S-curve.
 |
 |
Monte
Carlo cost risk analysis is particularly useful
at strategic points during a project when managers
need a realistic understanding of the eventual project
cost. They can also be used to distinguish between
targets (by which a realistically low cost outcome
might be incentivised) and expected costs or commitments.
A number of major risk-mature organisations use this
type of analysis routinely as part of their governance
processes. For example this type of information might
be used in evidence to support a major project go
/ no go decision. However, it is important that any
analysis required to support such decisions is conducted
to a high standard.
Performing
cost risk analysis to a high standard is
likely to involve a number of challenges. Typically,
these include:
•
Structuring the cost risk model so as to
avoid duplications of risk impact, whilst ensuring
that all major sources of risk are included
• Discriminating between sources of cost outcome
uncertainty and sources of risk events
• Making realistic estimates for the uncertainties
(most estimates tend to be too narrow)
• Making realistic probability and impact
estimates for risks
• Including appropriate degrees of correlation
within the model
The
problem of model structuring is often overlooked.
A symptom of weak risk analysis is a cost risk
model formed by importing every cost-related
risk from the risk register. This structure assumes
that the overall risk is equal to the sum of the parts.
Whilst this may be a reasonable simplifying assumption
for simple projects, it quickly becomes irrational
on the type of large or complex projects for which
Monte Carlo analysis is often considered
to be worthwhile. A typical problem is that risks
that impact on both time and cost can result in duplications
in the cost risk model. For example, if the
project is exposed to so-called “marching army”
risks concerned with the retention of parts of the
project team for longer than planned, then the inclusion
of such estimates in multiple risks may result in
duplications during some simulations. The time / cost
variances area at the bottom of the cost model figure
above shows lines related to this type of effect.
A similar approach may be needed for other time-driven
risks such as liquidated damages liabilities.
More
detailed advice on structuring cost risk models
can be obtained from papers that can be downloaded
from this site or from the APM’s PRAM
Guide.
Pertmaster
and @RISK for Excel are both suitable tools for cost
risk analysis. Further details on these and other
risk tools can be found at www.risktools.com.
Contact:
martin.hopkinson@hvr-csl.co.uk